Building a stronger water network for Newbridge’s growing community

Irsko Uisce Éireann Autor neuveden
A water network project between Two Mile House and Great Connell is nearing its final stages, with more than 7.5km of new water main installed along the 10km route. The investment will increase capacity and resilience to support future housing and growth in Newbridge and improve reliability for existing customers. Phased road closures continue, with a temporary lift from 18 December 2026 to 4 January 2027; works are expected to be completed in 2027.
AI shrnutí

A major water network project between Two Mile House and Great Connell is nearing its final stages, with more than 7.5km of new water main installed. The investment will increase capacity and resilience to support Newbridge’s future housing and growth.

Information below is relevant until further updates are provided here or on our Supply and Service Updates section

The Newbridge area is set to benefit from increased water network capacity and resilience as a major infrastructure project between Two Mile House and Great Connell moves into its final stages. More than 7.5km of new water main has now been installed along the 10km route.

Our investment will increase capacity in the local water network to support future housing and planned growth. The new pipeline will also reduce pressure on the existing network, helping to provide a more reliable water supply for existing customers in the area.

Speaking about the project, Uisce Éireann’s Derek Deignan, said: “We’re making great progress since works began in April, with 7.5km of the new water main now in place. Permanent road resurfacing and line marking have been completed between Corbally and Two Mile House.

“We’re now moving into the final stages of the project and appreciate the patience of the local community while we complete this work. This is an important investment in Newbridge’s water infrastructure, increasing capacity in the network to help support new homes and the continued growth of the area.”

To give our crews the space they need to complete the remaining work safely, phased temporary road closures will continue along the route. Works are currently taking place on Harbour Road before progressing to Great Connell Road towards Newbridge early next year.

The road closure will be temporarily lifted from 18 December 2026 until 4 January 2027, allowing normal access for residents, visitors and local traffic over Christmas.

We know road closures and construction activity can be disruptive, particularly for people living and travelling along the route. We appreciate the patience shown by the local community while this work continues and our crews will do everything they can to keep disruption to a minimum.

Works are being carried out on behalf of Uisce Éireann by Shareridge and are expected to be completed in 2027.

Some short-term water supply interruptions may also be required as work progresses. Where a planned interruption is needed, we'll give customers a minimum of 48 hours’ notice.

Customers can stay informed about their local water service by checking the supply and service section of our website, checking our live feed at X @IWCare, or signing up to receive real-time text updates. Our customer care team is also available 24/7 at 1800 278 278.