18.11.2026 22:41

Ballyheigue’s permanent water supply solution moves to construction

Irsko Uisce Éireann Autor neuveden
Uisce Éireann is investing more than €5 million in a permanent water supply solution for Ballyheigue, including 6.7 km of new watermain from Ardfert South to the water treatment plant. Construction is scheduled to begin in the week of 23 November and is expected to take four to six months. The Do Not Consume Notice, introduced in early October after saltwater entered the raw water source, remains in place for affected customers while alternative supplies continue; partial lifts have benefited approximately 340 customers.
AI shrnutí

Uisce Éireann investuje více než 5 milionů eur do trvalého řešení zásobování vodou pro Ballyheigue, včetně výstavby 6,7 km nového vodovodu. Práce mají začít v týdnu od 23. listopadu a dokončení se očekává za čtyři až šest měsíců.

Uisce Éireann is investing over €5 million to deliver a permanent, long-term water supply solution for the Ballyheigue community. This follows the introduction of a Do Not Consume Notice in early October due to saltwater ingress at the raw water source supplying Ballyheigue Water Treatment Plant.

A key part of the investment is the delivery of 6.7km of new watermain from Ardfert South to Ballyheigue Water Treatment Plant, with the project scheduled to commence the week of 23 November. The works are expected to be completed within four to six months. Every opportunity to accelerate delivery and shorten this timeframe will be explored as the project progresses.

Jack Cronin, Programme Manager with Uisce Éireann, said: “We are keen to get boots on the ground next week and move forward with this important investment for Ballyheigue. Delivering 6.7km of new watermain is a significant undertaking, but our focus is firmly on providing a lasting solution for the community.”

“Construction will begin on the first 1.2km of new watermain at Ardfert South, where site investigations are complete and the design has been finalised. The rest of the project will be delivered in sections. Construction methods will suit local ground and site conditions, with techniques that avoid digging an open trench used where appropriate to minimise disruption. The works are forecast to be completed within four to six months with all efforts to reduce this timeline further to be examined throughout the delivery.”

The works will be carried out on behalf of Uisce Éireann by its delivery partner, Shareridge Ltd. The project will provide a stronger, more secure and resilient water supply for homes, businesses and the wider community.

Supporting customers while actioning a permanent solution
While this investment represents significant progress towards securing Ballyheigue's long-term water supply, the Do Not Consume Notice remains in place for affected customers.

We are cognisant of the impact the notice is having on the community, there is also continued investment in supplying alternative water supplies and water distribution arrangements alongside temporary supply arrangements.

Brian O'Leary, Operations Manager with Uisce Éireann, said: “We fully recognise the considerable disruption a Do Not Consume Notice causes for families, businesses and the wider community, and understand the impact it continues to have on everyday life in Ballyheigue. Since the notice was introduced in early October, our priority has been to deliver improvements while progressing a permanent, long-term water supply solution. Our hydrogeologists, engineers, water quality specialists and operational teams have been working closely together to explore every available option, with a clear focus on safely restoring normal water supplies to as many customers as possible while delivering a lasting solution for the community.”

“While we are now progressing the permanent, long-term solution through 6.7km of new watermain, our efforts to restore normal water supplies to as many customers as possible continue in parallel."

“We have already made some progress, with two partial lifts of the notice benefiting approximately 340 customers. This includes approximately 200 customers in Causeway village and a further 140 customers from Banna and Lerrig Cross to Fortwilliam. We remain committed to building on this progress and reducing the impact on the wider community,” said Brian.

He said: “Work is progressing at Glenderry, which has the potential to benefit a further 170 customers. While we await the latest water quality results, any decision to restore the supply will be guided by the HSE and EPA, with public health remaining our absolute priority.”

Borehole drilling works are well advanced on the Ballyheigue Water Treatment Plant site and network management works are continuing to maximise existing supplies from Listowel and the Central Regional supply.

"Every customer who can safely return to using their water as normal represents meaningful progress for the community, and we will continue working towards that goal,” said Brian.

Alternative water supplies remain available
Uisce Éireann is reassuring customers that alternative water supplies will continue to be provided while the Do Not Consume Notice remains in place.

Water tankers are available 24/7 at the designated locations of Causeway Church Car Park, Kilmoyley Church Car park, Ballyheigue Beach car park, Ballyheigue old graveyard and Cantillon’s Cross, Kerry Head. Manned bottled water stations are operating at the same locations, on weekdays from 11.30pm to 2pm and 5.30pm to 8pm and at weekends from 11am to 2pm.

Deliveries to registered vulnerable customers will also continue. These arrangements will remain in place for as long as the Do Not Consume Notice is in place.

Customers can stay informed about their local water service by checking the supply and service section of our website, checking our live feed at X @IWCare, or signing up to receive real-time text updates. Our customer care team is also available 24/7 at 1800 278 278.



https://www.water.ie/news/ballyheigues-permanent-water-supply-solution-moves-construction
Autor
Společnost / Organizace
Uisce Éireann
Stáhnout
Sdílet