Centrica Business Solutions has completed a new Energy Centre at Solihull Hospital, the latest milestone in a 20-year partnership to improve energy efficiency and reduce emissions. The heat pump system and previous energy-saving measures are expected to meet 85% of the hospital’s heating needs, cut carbon emissions by 1,812 tonnes a year and save around £62,000 annually. The project was built while the hospital remained operational and was funded through the Department for Energy Security and Net Zero’s Public Sector Decarbonisation Scheme, with Salix as delivery body.
AI shrnutí

Centrica dokončila nové energetické centrum v nemocnici Solihull, jehož tepelné čerpadlo a další opatření mají pokrýt 85 % potřeby tepla. Očekává se snížení emisí o 1 812 tun ročně a úspora nákladů na energie přibližně 62 000 liber ročně.

  • Construction now complete, providing significant carbon reduction and cost savings

  • Along with previous energy efficiency improvements, carbon emissions will be cut by 1,812 tonnes a year and deliver £62,000 in annual energy cost savings.

Centrica Business Solutions has completed a new Energy Centre at Solihull Hospital, marking the latest major milestone in a two-decade partnership to reduce the hospital estate’s carbon emissions and improve its energy efficiency.

The new Energy Centre features an energy-efficient heat pump system, replacing the hospital’s existing electricity and heating infrastructure, and builds on a series of energy efficiency and decarbonisation measures that Centrica Business Solutions has already delivered at the site. Previous improvements have included the installation of cavity wall insulation, optimisation of their Building Management System, and the replacement of 2,500 lights with low power LEDs.

“Hospitals need reliable energy around the clock, and we’re proud to play our part in helping Solihull Hospital use cleaner energy and move towards a lower-carbon future.”

Matt Wood, Centrica Business Energy & Services Director

Together, these measures will meet 85% of the hospital’s heating requirements and reduce its carbon emissions by 1,812 tonnes a year. They are also expected to deliver annual energy cost savings of around £62,000.

The Energy Centre was built within a fully operational hospital that operates 24/7, requiring careful planning to minimise disruption to patients, staff and visitors throughout construction.

Matt Wood, Centrica Business Energy & Services Director said:

“We’re really proud to have worked with Solihull Hospital on this transformation. After 20 years of working together, it’s great to see our partnership continue to deliver practical changes that will help the hospital meet its significant energy needs while reducing its carbon emissions.

“Hospitals need reliable energy around the clock, and we’re proud to play our part in helping Solihull Hospital use cleaner energy and move towards a lower-carbon future.”

Martin Richardson, Executive Director at Solihull Hospital, part of University Hospitals Birmingham NHS Foundation Trust, said:

“The completion of the new Energy Centre is an important step in our work to make Solihull Hospital more energy efficient and reduce the carbon footprint of our estate.

“Working with Centrica over many years has enabled us to continually improve our energy infrastructure, and this latest project will deliver significant reductions in carbon emissions and costs, while providing the heating our hospital needs.”

The energy reduction measures were funded through the Department for Energy Security and Net Zero’s Public Sector Decarbonisation Scheme, with Salix as the delivery body and development and procurement undertaken through the Carbon and Energy Fund (CEF).

CEF supports NHS trusts and public body organisations to improve energy infrastructure and reduce overall emissions.

Andy Yates, Director of Projects at The Carbon and Energy Fund (CEF) said:

"The Carbon and Energy Fund have been proud to support University Hospitals Birmingham to deliver this exciting site wide de-carbonisation project as part of our wider strategy across the Trust.

"This successful project, funded by DESNZ and Salix under a PSDS 3c grant, delivered by our Framework Contractor Centrica Business Solutions delivers a step change for the site. Transitioning away from CHP to a cascade heat pump system to deliver carbon savings, meeting the NHS 2032 target whilst working within tight timescales, capital envelope and revenue budget."